Ukrnafta wants to buy three cogeneration units with a capacity of 72 MW or more for UAH 2.56 billion
Ukrnafta PJSC has announced tenders to purchase three gas-piston cogeneration units with a total capacity of at least 72 MW, the company's press service reports. The total expected cost of the purchase and installation of the generating units is UAH 2.56 billion (excluding VAT).
The deadline for submitting bids is July 27, and the auction will start on July 29, 2024. The term of delivery of goods, their installation, and commissioning is expected to be by December 31, 2024.
The first unit should have a capacity of 27-30 MW, three gas piston engines, and an electrical efficiency of at least 46%. The expected cost is UAH 960 million (excluding VAT).
The second unit will have a capacity of 27-30 MW, three gas piston engines, and an electrical efficiency of at least 46%. The expected cost is UAH 960 million (excluding VAT).
The third unit will have a capacity of 18-20 MW, two gas piston engines, and an electrical efficiency of at least 46%. The expected cost is UAH 640 million (excluding VAT).
All three plants must be new and have appropriate remote control and security systems. The warranty for each unit is at least 24 months from the date of delivery.
Installation, supervision of installation, commissioning, testing, commissioning, and training of personnel will be provided by the supplier.