UGV we plan to recover UAH 285 600 from Ukrgrandpol LLC for untimely delivered goods
The JSC Ukrgaіvydobuvannya, represented by its branch Ukrburgas Drilling Division, filed their claim with the Commercial Court of Poltava region for recovery of UAH 285 600 from the Ukrgrandpol LLC for incomplete delivery of goods and services under the agreements from 12.02.2019.
On February 12, 2019, the Parties entered into agreements on supply of KNT 5500 (TEDA hydraulic wrenches for bending production tubing and YZBF-120LD-2 (TEDA) electric drive hydraulic power units .The total cost of the good contacted was UAH 10.2 million (incl. 20 % VAT).
According to the agreement, the Ukrgrandpol LLC undertook within 120 days from the date of the contract to deliver the necessary goods to the Krasnogad base of production and technical support of the Ukrburgas Drilling Division in the Kharkiv region .
The court accepted the statement of claim for consideration and opened proceedings in the case. The preparatory meeting was scheduled for 15.07.2020.