DTEK Naftogaz will drill two more wells at Machukhske field
Naftogazrozrobka LLC, group of DTEK Naftogaz, intends to drill exploration wells No. 57 and No. 59 at the Machukhske gas condensate field (GCF) and develop the wells. This was reported in the EIA Register on December 19, 2019.
According to the report, it is planned to drill, equip and tie-in the wells. In addition, wells entry manifolds at Machukhske Gas Treatment Plant (GTP) will be extended and a parallel gas pipeline will be constructed from Machukhske GTP to the Dykanka-Kremenchuk-Kryvyi Rih main gas pipeline with a length of 6,209m. The reconstruction of the second stage of the Machukhske GTP is also planned. In particular, it includes the construction of a third process line for the low-temperature gas separation (NTS-3).
According to anEIA Register report, drilling of well No. 57 with depth of 5,520m (target horizon C1tb-d (T-2-4)) is planned to be performed with a Bentec 450 (RIG 2000 HP) drilling rig with a lifting capacity of 450 tons and diesel drive. And drilling of the well No. 59 with a depth of 5,900m (target horizon F-1-2 (D3fm)) will be performed with Drillmec 1500 HP Winter drilling rig with a lifting capacity of at least 345 tons and diesel drive.